June 27, 2022 - A-Tech contractors will not be working today due to the storms expected this morning. Work resumes tomorrow, June 27,2022.
June 24, 2022
For the week of June 27 - July 1, 2022 - A-Tech will be on site and begin demo and reconstruction from Hudson Ave to Cedar Hill Ave. The vault work is complete and this area is a high priority for completion - it is on schedule to be completed by the weekend of July 9, 2022.
June 16, 2022
For the week of June 20, 2022 - June 24, 2022 A-Tech contractors will not be in the Village. They are expected back in the Village the week of June 27, 2022.
June 11, 2022
For the week of June 13 - June 17, 2022 A-Tech contractors plan to work only in the vaults at #76 & #78 South Broadway. No other work is planned for the week.
June 4, 2022
Work will continue in the vaults on the west side of the street between Hudson Ave and Cedar Hill Ave. Concrete for curbs and sidewalks is expected in the beginning of the week, weather permitting from Cedar Hill to the gas station property. Thank you for your continued cooperation and patience with the project.
IMPORTANT - PLANS CHANGED AS OF MAY 31, 2022:
Work schedule has changed this week to include the saw cutting of the roadway from Hudson Ave to Cedar Hill Ave (west side). Curb and asphalt removal from Cedar Hill Ave to the gas station. Additionally, work in the vaults will continue.
May 27, 2022: Asphalt repairs will be made to the roadway between Cedar Hill Ave and Hudson Ave today and concrete is also being poured which will complete the sidewalks from Maura's Kitchen to Cedar Hill Ave.
No work on Monday, May 30, 2022 - Memorial Day Holiday
At this time (5.27.22 11:00am) there is no sidewalk work planned for next week 5/31/22 - 6/3/22
The contractor will be working in vaults next week on the west side of S. Broadway from Hudson Ave to Cedar Hill Ave.
Check the website for updates.
Work continues on the east side of South Broadway between Maura's Kitchen and Cedar Hill Ave. The walkway part of the sidewalk should be finished by Friday, 5/27/22. Due to limited availability of concrete, the "buffer" strip will be completed next week. Asphalt is scheduled to be patched in this week on the east side.
May 20, 2022
The curb is finished from Hudson Ave to Cedar Hill Ave. The concrete sidewalk has been removed from Maura's Kitchen to Cedar Hill Ave. New sidewalk is expected to be poured on Tuesday, May 24, 2022 , weather permitting. Asphalt repairs will be made during the week of May 23, 2022. The contract will finish the east side of the street and then will break until after the Memorial Day holiday. After May 31, 2022 work will start on the west side of the street heading north to Depew Ave.
May 13, 2022
Work continues on South Broadway between Hudson Ave and Maura's Kitchen. New curbs have been formed and the sidewalk excavated. Concrete is expected to be poured on Tuesday, May 17, 2022. The work will progress in front of Maura's Kitchen south to Cedar Hill Ave next week. Vault work on the west side of the street will continue next week.
May 6, 2022
Weather today is preventing the paving of the gutter in front of the library. This will be done next week.The sidewalk and parking will be accessible over the weekend, with safety cones to prevent accidents in the unpaved gutter.May 5, 2022
The concrete sidewalk between Depew Ave and Hudson Ave (east side) is scheduled for a concrete pour today. This will complete that first section of the project and sidewalks will be fully open by tomorrow in that area. The next phase of the project will occur between Hudson Ave and Maura's Restaurant - approximately half the block. Saw cutting will occur on Friday, May 6, 2022 for curb and sidewalk sections. Demolition of this area is scheduled to begin on Monday, May 9. 2022. Sidewalks are expected to be fully open for the weekend. There will be parking restrictions on the east side during the construction. Thank you for your patience and cooperation!!
May 1, 2022
Work continues on South Broadway. Concrete sidewalk is expected to be poured on Tuesday, May 3, 2022 from Depew Ave to Hudson Ave. Updates will be posted daily.
April 26, 2022
CONSTRUCTION HAS BEGUN!!! Currently, the contractor is working on demolition of the sidewalk between Depew Ave and Hudson Ave on the east side of the road. There is work underway on a underground vault at 73 S. Broadway. This is necessary to rebuild a new sidewalk. There are a number of vaults under South Broadway that will need to be structurally reinforced before the sidewalk work can move forward.
Monday 4/26 - Staging equipment & saw cutting into pavement between Depew Ave & Hudson Ave.
Tuesday 4/27 - Demolition of curb in work zone
Wednesday 4/28 - Forms constructed for curbing
Thursday 4/29 -Continued demolition of sidewalks, work at 73 S. Broadway vault
Friday 4/30 - Demolition of sidewalks
Work is expected to last 1-2 weeks in this area. Check back for updates!
April 22, 2022
CONSTRUCTION WILL START ON MONDAY, APRIL 25, 2022!! The work on the vaults will be delayed a few days, so in an effort to get the project moving quickly through the area, the contractor will start work on Monday, April 25, 2022 on sidewalks and curbs. Thank you for your cooperation and patience with this project!!
Monday, April 25, 2022: Survey and mobilization will begin on South Broadway and Depew Ave. No parking restrictions necessary.
Tuesday, April 26, 2022: Demolition will begin on the east side of the street - both corners on the east side of Depew Ave and South Broadway. The contractor will maintain access to all properties during construction. Parking restrictions will be posted in advance.
April 20, 2022
Updates to the start of sidewalk construction on South Broadway: Construction work will begin at 73 S. Broadway on Monday, April 25, 2022. This work is to prepare the underground property (vaulted area) for the new sidewalk. The work consists of vault reinforcement and the vault will be accessed from inside the building. Once the vault is stabilized (2-5 working days) construction will then start on the sidewalks beginning at South Broadway and Depew Ave. The construction work will begin on the east side of the street - both corners on the east side of Depew Ave and South Broadway. The project will work south to Cedar Hill Ave and then circle back on the west side of the street. Each block is expected to take 1 -2 weeks.
Parking Authority will post any parking restrictions in the area in advance of the work.
The contractor will maintain access to all properties during construction. Updates will be posted frequently, please check back for more information.
April 14, 2022
Survey work will begin next week, Tuesday, April 19, 2022 in the South Broadway area. This work will have no impact on parking. Construction work is scheduled to begin the week of April 25, 2022. The work will begin at South Broadway and Depew Ave - on the east side of the street - both corners on the east side of Depew Ave and South Broadway. Parking Authority will post any parking restrictions in the area in advance of the work. The contractor will maintain access to all properties during construction.
March 28, 2022
The sidewalk reconstruction project will tentatively resume the week of April 18, 2022. The contractor will begin construction at the corner of Depew Ave, on the east side of South Broadway. The work will continue south until Cedar Hill Ave, and then resume on the west side of the street from Cedar Hill Ave heading north on S. Broadway to Depew Ave. A number of vaults have been identified and will need to be prepared for the sidewalk construction. The contractor may have a "vault" crew working separately from the sidewalk crews to prepare these vaults so that the project can move quickly through any vaulted areas. This work is located in the basement areas of specific buildings and will not impede the use of the sidewalks above the vaults. Additionally, the contractor will make every attempt to minimize the impact to parking. Any questions - please contact Village Administrator, Andy Stewart, at 845-358-3581.
February 10, 2022
The Village of Nyack will be holding a ZOOM workshop tonight – there is a link on the website – www/nyack-ny.gov/calendar. The meeting starts at 6:30pm. The Engineers will be on the meeting to discuss changes in the project. Work is expected to resume by mid to late March 2022. Spring construction will start between Cedar Hill Avenue and Depew Ave. The contractor will be working one block at a time and will coordinate closely with businesses and residents to maintain access at all times.
Everyone is welcome to join the Zoom call this evening to hear more details. Questions and concerns welcomed.
If your building has a vault (cellar) underneath the sidewalk – please notify the Village Administrators office as soon as possible!! Any questions, please contact: Jim Politi, Interim Village Administrator
February 1, 2022:
The Broadway Streetscape & Sidewalk project will be resuming construction in early spring 2022 on South Broadway between Cedar Hill Avenue and Depew Avenue. The contractor will be working closely with residents and businesses to maintain access at all times. A construction schedule will be available in the coming weeks. This information will be distributed by flyers and updated on the the village website, www.nyack-ny.gov. If your building has a basement stairwell from the sidewalk or a vault or storage area under the sidewalk, please reach out to the Village Administrator’s office as soon as possible. A site visit by the engineers will need to be scheduled ASAP.
November 22. 2021:
Sidewalk work has finished for the season. The contractor will be working closely with the engineers over the winter months to review all plans and prepare for Spring 2022 restart.
Any questions, please contact the Village Administrator's office at 845-358-3581.
November 17, 2021:
Work resumes today on the North Broadway sidewalk between High Ave and First Ave today. DOT approved changes to reduce the slope of the sidewalk, yet maintain an ADA compliant sidewalk. Concrete will be poured on Thursday, November 18, 2021. No other sidewalk work will take place over the winter months. Work will resume as early in the spring as the weather allows. Thank you to all our residents at Victoria Mews, who have been very patient and cooperative during this process.
November 12, 2021:
The median island on North Broadway has been removed at the discretion of the Village Board. A redesigned "bump-out" crosswalk will be constructed in this area in the Spring 2022. At this time we are waiting for DOT approval on the redesign of this area. Updates will be posted as they become available. The sidewalk on N. Broadway between High Avenue and First Avenue is also being redesigned to address the slope, we expect to have construction resume the week of November 15, 2021.
Statement from the Mayor and Village Board:
Over the past few weeks we have been experiencing some inexcusable issues with the engineering firm and aspects related to the Broadway Streetscape Project. We have been and will continue to pursue every option available to ensure these issues are remedied and that potential issues are identified and remediated before any future work proceeds.
This has been a frustrating process from the very beginning of this project. We still see the possibilities of a wonderful upgrade for Broadway. Another in a series of upgrades that makes our village pedestrian friendly and safe. More details on the Broadway Streetscape
October 29, 2021: Unfortunately the sidewalk project has hit a setback. The partially constructed sidewalk along North Broadway between First Ave and High Ave will have to be demolished and rebuilt. The original design was engineered to comply with DOT regulations for a five foot wide walkway, however, it resulted in an unacceptable slope past the walking path to the curb. We have ordered the contractors to stop work while the Village works with engineers and the DOT on a remedy. The contractors will be back on site this week to rebuild the sidewalk.
Update on the median island on North Broadway: The Village Board decided on October 28, 2021 to remove the median island. It will be replaced with "bump-outs" on the west and east side of the North Broadway in addition to a crosswalk. The contractor will be back on site beginning November 1, 2021 to demolish the island. Reconstruction of this area will be scheduled for Spring 2022.
October 22, 2021: Sidewalk demo and prep work continues on N. Broadway between High Ave and First Ave. The crosswalk on North Broadway between Fourth Ave and Fifth Ave is under review and work is expected to resume next week. The contractor expects to finish the current work zones this fall. The project is expected take approximately a year to complete. We will update the schedule and post progress reports weekly while the construction is active. Expect a full shut down for winter months.
October 15, 2021:
On Monday, October 18, 2021, construction will begin on the sidewalk reconstruction project on the block of N. Broadway between First Ave and High Ave. Here’s what to expect when construction starts:
DELAYS HAVE PUSHED THE CONTRACTOR START DATE TO WEDNESDAY, OCTOBER 20, 2021
TENTATIVE SCHEDULE