Broadway Streetscape Update for week of May 9, 2022

May 6, 2022

  • Rain on Friday, May 6, 2022 prevented the paving of the street gutter in front of the library. This will be done next week.
  • The sidewalk and parking will be accessible over the weekend - please visit the restaurants and shops of SoBro this weekend!
  • Vault work at 73 S. Broadway has been completed, no further work scheduled there until the sidewalk gets poured.
  • Monday, 5/9, A-Tech will begin excavation of the curb from Hudson Avenue to Maura’s Restaurant.
  • Monday, 5/9, A-Tech will begin work on the vault in front of Pizza Bistro. Access will be maintained to the businesses.
  • Once curb is excavated, work can begin on excavating sidewalk (takes about a week and a half) and then moving on to new sidewalk cement, followed by paving the street gutter line.
  • The full process of the new sidewalk construction can take a couple of weeks, and can be impacted by weather and cement suppliers.
  • In the meantime, work will progress in the vaults on the west side of S. Broadway, one by one.
  • Village staff is meeting with contractors and inspectors daily for updates and conducts a full project review every other week.
  • This update is published on the village website. Follow the project here.